McNary-Roundup Transmission Line Rebuild Project



The following comments were submitted in response to the open comment period described below.

Comments are numbered consecutively as they are received. Breaks in the number sequence result when comments are deleted because they were submitted in error or have inappropriate content (such as SPAM). If you do not see your comment two business days after you submit it, please contact (800) 622-4519.

BPA proposes to rebuild its existing 38.5-mile-long, McNary to Roundup No.1 230- kV transmission line in Umatilla County, Oregon. The wood-pole line connects the BPA McNary Substation in Umatilla, Oregon, to the BPA Roundup Substation near Pendleton, Oregon. The transmission line has been in service for about 70 years and needs to be rebuilt to ensure reliable electric service and the safety of the public and transmission workers who operate and maintain the line. Your comments will help BPA determine the issues that should be addressed in the environmental review.

For More Information:
http://www.bpa.gov/nepa/mcnary-roundup

Close of comment:  3/24/2024

  • MRTL-24240001 -  Remillard

  • MRTL-24240002 -  pace

  • MRTL-24240003 -  Ball

  • MRTL-24240004 -  Pierson

  • MRTL-24240005 -  Bonney

  • MRTL-24240006 -  Roth

  • MRTL-24240007 -  FOUTZ/City of Umatilla

  • MRTL-24240008 -  Williams

  • MRTL-24240009 -  Morris

  • MRTL-24240010 -  Elfring

  • MRTL-24240011 -  Terry

  • MRTL-24240012 -  Ramos

  • MRTL-24240013 -  Green/USFWS

  • MRTL-24240014 -  Somers/Oregon Dept. of Fish and Wildlife

  • MRTL-24240015 -  Kirkpatrick/Hermiston Irrigation District